Process-domain program report

The year's projects rolled up by process domain and project chain — budget consumption, resource utilisation, business output and quarterly delivery.

Process domains
6
Projects
26in cycle
Actual mandays
1,994.5year to date
Overall execution
95.4%actual ÷ est
Business output
5,742.5×10k CNY
Portfolio ROI
175.9%benefit ÷ invest

Project portfolio

Project
Q1actual / est
Q2actual / est
Q3actual / est
Q4actual / est
Exec rateLatestBaseline
(5) 218.9 / 192.9(3) 78.0 / 71.4(3) 51.1 / 70.5(2) 27.1 / 29.2103.0%
Turbine 6MW Platform Phase 3PRJ-1000 · Firmware 3.0
16.8 / 10.111.0 / 13.217.2 / 16.66.3 / 14.294.9%2026-04-172026 Q3 · 57.1
Flab Redesign Wave 2PRJ-1001 · Firmware 3.0
22.8 / 13.419.5 / 22.912.3 / 17.520.9 / 15.1109.6%No update2026 Q3 · 64.1
Flab Redesign Wave 3PRJ-1002 · Firmware 3.0
61.8 / 60.3———102.4%2026-10-11—
Firmware 3.0 Wave 3PRJ-1003 · Flab Redesign
31.7 / 34.847.4 / 35.321.5 / 36.4—94.6%2026-07-012026 Q3 · 106.9
Turbine 6MW Platform Track 2PRJ-1004 · Flab Redesign
85.7 / 74.2———115.5%2026-07-24—
(5) 316.8 / 292.4(4) 117.0 / 147.5(2) 48.2 / 56.2—97.1%
Site Commissioning Phase 1PRJ-1005 · Grid Connection
25.2 / 31.631.4 / 35.2——84.7%No update—
Site Commissioning Phase 3PRJ-1006 · Site Commissioning
163.4 / 144.0———113.5%2026-02-032026 Q1 · 147.9
Grid Connection Track 2PRJ-1007 · EPC Fast-track
44.8 / 36.532.2 / 41.0——99.3%2026-02-052026 Q2 · 75.2
Site Commissioning Phase 2PRJ-1008 · Site Commissioning
60.6 / 53.429.8 / 39.231.6 / 29.6—99.9%2026-05-23—
Grid Connection Track 2PRJ-1009 · Grid Connection
22.8 / 26.923.6 / 32.116.5 / 26.5—73.5%2026-07-212026 Q3 · 81.0
(4) 160.5 / 175.9(3) 60.5 / 87.8(3) 75.5 / 83.9(2) 38.1 / 44.685.3%
Supplier Portal Wave 2PRJ-1010 · Supplier Portal
8.8 / 10.05.6 / 14.114.5 / 13.8—76.2%No update2026 Q3 · 39.2
Supplier Portal Phase 2PRJ-1011 · Supplier Portal
87.6 / 87.9———99.6%2026-07-142026 Q1 · 83.8
Logistics Control Tower Wave 1PRJ-1012 · Supplier Portal
24.9 / 40.127.5 / 19.920.8 / 47.212.9 / 17.269.2%2026-09-052026 Q3 · 133.6
Logistics Control Tower Track 1PRJ-1013 · Logistics Control Tower
39.3 / 37.927.5 / 53.840.2 / 22.925.2 / 27.493.0%2026-03-262026 Q3 · 150.6
(4) 123.5 / 114.6(4) 120.6 / 139.7(2) 88.8 / 50.2(1) 28.9 / 16.6112.7%
Quality Traceability Phase 3PRJ-1014 · Quality Traceability
22.9 / 20.015.6 / 15.8——107.8%No update2026 Q2 · 35.0
Smart Factory Track 2PRJ-1015 · Quality Traceability
24.8 / 28.641.6 / 44.546.8 / 22.4—118.7%2026-09-222026 Q3 · 101.1
Quality Traceability Wave 1PRJ-1016 · Smart Factory
21.6 / 25.420.7 / 26.342.0 / 27.928.9 / 16.6117.6%2026-09-162026 Q3 · 86.9
Quality Traceability Track 1PRJ-1017 · Smart Factory
54.2 / 40.642.7 / 53.1——103.4%2026-06-10—
(3) 54.2 / 74.9(3) 59.9 / 62.5(2) 43.0 / 37.1—90.0%
Spare Parts Planning Wave 2PRJ-1018 · Spare Parts Planning
9.8 / 13.919.7 / 14.919.3 / 17.6—105.0%No update2026 Q3 · 48.3
Remote Diagnostics Phase 1PRJ-1019 · Remote Diagnostics
19.9 / 18.811.5 / 18.023.6 / 19.5—97.5%2026-06-142026 Q3 · 57.2
Remote Diagnostics Wave 3PRJ-1020 · Spare Parts Planning
24.6 / 42.128.7 / 29.6——74.3%2026-10-032026 Q2 · 67.6
(3) 55.6 / 62.7(3) 44.5 / 53.1(1) 11.5 / 24.4(1) 18.5 / 19.881.3%
Cost Allocation Track 3PRJ-1021 · Budget Cockpit
22.4 / 17.611.5 / 16.911.5 / 24.418.5 / 19.881.3%No update—
Cost Allocation Track 2PRJ-1022 · Cost Allocation
11.1 / 17.214.3 / 13.9——81.5%2026-05-222026 Q2 · 32.5
Budget Cockpit Wave 3PRJ-1023 · Cost Allocation
22.1 / 27.918.7 / 22.3——81.2%No update2026 Q2 · 53.8
(2) 126.5 / 137.3(1) 11.9 / 18.4(1) 6.2 / 9.1(1) 9.4 / 18.084.2%